Skip to content

Instantly share code, notes, and snippets.

@quawn
Last active September 10, 2024 19:41
Show Gist options
  • Select an option

  • Save quawn/8503445 to your computer and use it in GitHub Desktop.

Select an option

Save quawn/8503445 to your computer and use it in GitHub Desktop.

Revisions

  1. quawn renamed this gist Jan 22, 2014. 1 changed file with 0 additions and 0 deletions.
    File renamed without changes.
  2. quawn renamed this gist Jan 19, 2014. 1 changed file with 0 additions and 0 deletions.
    File renamed without changes.
  3. quawn created this gist Jan 19, 2014.
    72 changes: 72 additions & 0 deletions gistfile1
    Original file line number Diff line number Diff line change
    @@ -0,0 +1,72 @@
    <?php
    function getWorkingDays($startDate,$endDate,$holidays) {
    // do strtotime calculations just once
    $endDate = strtotime($endDate);
    $startDate = strtotime($startDate);


    //The total number of days between the two dates. We compute the no. of seconds and divide it to 60*60*24
    //We add one to inlude both dates in the interval.
    $days = ($endDate - $startDate) / 86400 + 1;

    $no_full_weeks = floor($days / 7);
    $no_remaining_days = fmod($days, 7);

    //It will return 1 if it's Monday,.. ,7 for Sunday
    $the_first_day_of_week = date("N", $startDate);
    $the_last_day_of_week = date("N", $endDate);

    //---->The two can be equal in leap years when february has 29 days, the equal sign is added here
    //In the first case the whole interval is within a week, in the second case the interval falls in two weeks.
    if ($the_first_day_of_week <= $the_last_day_of_week) {
    if ($the_first_day_of_week <= 6 && 6 <= $the_last_day_of_week) $no_remaining_days--;
    if ($the_first_day_of_week <= 7 && 7 <= $the_last_day_of_week) $no_remaining_days--;
    }
    else {
    // (edit by Tokes to fix an edge case where the start day was a Sunday
    // and the end day was NOT a Saturday)

    // the day of the week for start is later than the day of the week for end
    if ($the_first_day_of_week == 7) {
    // if the start date is a Sunday, then we definitely subtract 1 day
    $no_remaining_days--;

    if ($the_last_day_of_week == 6) {
    // if the end date is a Saturday, then we subtract another day
    $no_remaining_days--;
    }
    }
    else {
    // the start date was a Saturday (or earlier), and the end date was (Mon..Fri)
    // so we skip an entire weekend and subtract 2 days
    $no_remaining_days -= 2;
    }
    }

    //The no. of business days is: (number of weeks between the two dates) * (5 working days) + the remainder
    //---->february in none leap years gave a remainder of 0 but still calculated weekends between first and last day, this is one way to fix it
    $workingDays = $no_full_weeks * 5;
    if ($no_remaining_days > 0 )
    {
    $workingDays += $no_remaining_days;
    }

    //We subtract the holidays
    foreach($holidays as $holiday){
    $time_stamp=strtotime($holiday);
    //If the holiday doesn't fall in weekend
    if ($startDate <= $time_stamp && $time_stamp <= $endDate && date("N",$time_stamp) != 6 && date("N",$time_stamp) != 7)
    $workingDays--;
    }

    return $workingDays;
    }

    //Example:

    $holidays=array("2008-12-25","2008-12-26","2009-01-01");

    echo getWorkingDays("2008-12-22","2009-01-02",$holidays)
    // => will return 7

    ?>